MARCH '06:
The concrete structure is complete, yet there are many things to do before the building is finished: insulation, paint, stucco, doors and windows, floors, bathrooms, kitchen appliances, air conditioning, etc. We are greatful you've been with us this far. Your contributions have a very significant impact in the outcome of the building and more importantly, in the lives of Colegio students. Keep us in your prayers and in your budgets!
|
|
FEBRUARY '06:
Most of the necesary lamps have been installed on the metal framing of the ceiling.
|
|
DECEMBER '05 - JANUARY '06:
The foyers have been completed and electrical wiring has been installed. Currently work is being done on the finishings of the kitchen ceiling.
Many thanks to all who continue to support the multipurpose building project with finances and prayers.
|
|
NOVEMBER '05:
Construction continues at a steady pace. The front and side foyers are now being built. Metal forms were manufactured to pour the concrete for the arches.
We are excited to see how this building takes shape and trust that God will continue to provide for this construction to be completed. This building will be a great blessing for Colegio students as they prepare for Christian ministry.
|
|
SEPTEMBER -OCTOBER '05:
Construction has resumed. The cement plaque above the kitchen area has been completed and the one above the bathrooms is being laid out.
Thank you so much for your gifts that make this work possibile!
|
|
JUNE-AUGUST '05:
Construction was paused for most of the summer because of the many activities during these months.
Still lacking are two cement plaques on both extremes of the building (one above the bathrooms, and the other above the kitchen) as are all the interior finishings.
|
|
MAY '05:
The roof of the multipurpose building was completed at the beginning of May. We thank God for his faithfulness in providing.
We still need your financial support to work on the electric wiring, wall finishings, doors and windows, tile floor, and equipment.
|
|
APRIL '05:
On March 28th the metal structure for the roof of the multipurpose building started going up. We still have a long way to go before this building on the Mexico Campus is complete. However, we are thankful to God for allowing us to move on to this new phase.
Many thanks to all who have responded to our need with great generosity; we pray it will be rewarded by our faithful Lord.
|
MARCH '05:
Currently, the multipurpose building is under construction. It will house the kitchen and dining hall and will be used for weekly chapel meetings, students' receptions, graduation, and other special events.On February 25, we gave a downpayment for the construction of the roof and its metal structure. By the month of May, we have to give two more payments; we've yet to raise $10,000 to complete this step. We thank God for having provided until now, and trust that He will continue to do so through out brothers and sisters in the faith.
|
|
|